Eighth uranium shipment arrives at Rooppur power plant
The eighth shipment of nuclear fuel uranium imported from Russia for the under-construction Rooppur Nuclear Power Plant in Ishwardi, Pabna, arrived at the project site early Tuesday.
The fuel consignment was transported to the project area in three specialised trucks, which arrived at 5:48am on Tuesday (November 24).
The trucks entered the project site under Army supervision and tight security provided by law enforcement agencies. Dr Md Kabir Hossain, project director of the Rooppur Nuclear Power Plant, confirmed the arrival of the shipment.
According to project sources, a total of eight shipments have now arrived in Bangladesh, including one additional fuel shipment for the plant's first unit and seven for the second unit. Under the plan of Russia's state-owned nuclear corporation Rosatom, 163 uranium assemblies are scheduled to be delivered in seven cargo aircraft for the second unit. Another 48 assemblies are planned to be brought in two cargo aircraft to refuel the first unit. The entire consignment is expected to arrive in nine shipments.
Built with Russian technology, the Rooppur Nuclear Power Plant has two VVER-1200 reactor units, each with a generation capacity of 1,200 megawatts. Once both units become fully operational, they will add a combined 2,400 megawatts of electricity to the national grid.
Meanwhile, the plant's first unit has begun its second round of trial electricity supply to the national grid. The process started at 10:20am on Monday (November 23). During this phase, the unit is supplying between 300 and 350 megawatts of electricity to the grid for testing periods ranging from 10 to 24 hours.
Earlier, the first unit was connected to the national grid for the first time at 3:16pm on November 17. Electricity generation was temporarily suspended at 11:50pm that night after more than eight and a half hours of continuous operation. The unit generated a maximum of 375 megawatts during that period.
Project Director Dr Md Kabir Hossain said the unit was supplying between 300 and 350 megawatts to the national grid during the second phase of testing, which would continue for 10 to 24 hours.
Project officials aim to begin supplying electricity at the first unit's full capacity of 1,200 megawatts to the national grid in the first half of next year, following the completion of necessary tests and monitoring. Under an agreement with the Russian contractor, commercial electricity generation will begin in phases after a 10-month trial operation period.