Final consignment of uranium reaches Rooppur

District  Correspondent

District Correspondent

Bangladesh has completed the scheduled import of nuclear fuel from Russia for the Rooppur Nuclear Power Plant, with the ninth and final shipment of uranium arriving at the project site in Ishwardi, Pabna, early on Friday (November 27).

The final consignment was transported to the plant in three specialised trucks at 5:48am, under tight security supervised by the army, with police and other law enforcement agencies also involved. The fuel was flown in from Russia on specialised cargo aircraft before being transported by road to the project site.

According to project sources, the plan included importing 48 uranium fuel assemblies as additional fuel for the plant's first unit and 163 assemblies for the second unit. The fuel for the second unit was delivered in seven shipments, while the additional fuel for the first unit arrived in two. The arrival of all nine shipments, in line with the plan of Russia's state-owned nuclear corporation Rosatom, marks the completion of the fuel supply process.

Built with Russian technology and assistance, the Rooppur Nuclear Power Plant has two units equipped with VVER-1200 reactors. Each unit has a generation capacity of 1,200 megawatts. Once both units are fully operational, they are expected to add a combined 2,400 megawatts of electricity to the national grid.

Meanwhile, alongside the completion of nuclear fuel imports, preparations for trial electricity generation and supply to the national grid from the plant's first unit are also progressing. The second phase of trial power supply began on November 23, when 300 to 350 megawatts of electricity were fed into the national grid at 10:20am.

According to project director Dr Md Kabir Hossain, the plan at this stage is to supply electricity for periods ranging from 10 to 24 hours to test the plant's generation systems and its operational coordination with the national grid.

The first trial supply of electricity from Rooppur's first unit took place on November 17. The trial generation began at 3:16pm and continued until 11:50pm. During the test, which lasted more than eight hours, the plant generated a maximum of 375 megawatts of electricity.

The arrival of all nuclear fuel shipments and the successive trial supplies of electricity to the national grid mark significant progress in the commissioning of the Rooppur project. However, the plant must complete the necessary technical tests, safety assessments and other preparations before both units can achieve their full generation capacity.