Metro rail services from Uttara to Kamalapur targeted for July 2027
Passengers will have to wait until July next year for direct metro rail services between Uttara and Kamalapur, as delays in completing the Motijheel-Kamalapur extension of MRT Line-6 have prompted another revision to the commercial operation schedule.
Under the latest plan, the project authorities aim to begin passenger services on the extended section in July 2027.
According to project sources, although construction of the extended section has progressed, key electrical and mechanical works remain incomplete. The authorities plan to begin passenger services only after completing the infrastructure, installing the necessary technical systems, and carrying out required tests and safety inspections.
According to Dhaka Mass Transit Company Limited (DMTCL), the operational section of the metro rail from Uttara North to Motijheel currently spans 20.10 kilometres. With the addition of another 1.16 kilometres from Motijheel to Kamalapur, the total length of MRT Line-6 will reach 21.26 kilometres, with 17 stations along the route.
As of September 30, 84.85 per cent of the civil construction work on the Motijheel-Kamalapur section had been completed, while 58 per cent of the electrical and mechanical works had been finished. The remaining major infrastructure and architectural works are scheduled for completion by December 31, 2026.
Construction of the elevated viaduct from Motijheel to Kamalapur, a key component of the project, has already been completed and handed over to the relevant contractor to prepare for track installation. The main structure of Kamalapur station has also been completed. Work is now underway on interior finishing, installation of electrical and mechanical equipment, and construction of passenger entry and exit facilities.
However, train operations cannot begin immediately after construction is completed. Seven integrated electrical and mechanical systems must be fully operational before the route can be opened to passengers. These include railway tracks, power supply, signalling and control, automated fare collection, platform screen doors, telecommunications, and lifts and escalators. The authorities will then conduct integrated system tests and trial runs to ensure safety and operational efficiency.
The timeline for extending the metro rail to Kamalapur has been revised several times. Initially, services on the section were scheduled to begin on January 1, 2027. The target was later shifted to April-May. However, considering progress in construction and associated technical works, July has now been set as the new target.
Once completed, the extension will bring Kamalapur, one of the capital's most important railway hubs, directly under the metro rail network. It will allow passengers to travel directly from Uttara to Kamalapur while making transfers between intercity trains and the metro rail easier for passengers using Kamalapur railway station.