Seventh uranium shipment arrives at Rooppur power plant
The seventh shipment of uranium imported from Russia for the second unit of the Rooppur Nuclear Power Plant in Ishwardi, Pabna, arrived at the project site on Friday, completing the scheduled transportation of nuclear fuel in seven consignments for the unit.
Three specialised trucks carrying the fuel entered the project site at 6:24am on Friday (November 20). The shipment was transported under tight security supervised by the Bangladesh Army, in coordination with other law enforcement agencies.
The trucks began their journey to Rooppur on Thursday night after arriving at Hazrat Shahjalal International Airport in Dhaka. They travelled via the Jamuna Bridge, Banpara in Natore and Dashuria in Ishwardi before reaching the project site.
Police were deployed at key locations along the route. Specialised security forces and intelligence agency personnel also joined the Army in ensuring the safe transportation of the fuel. To avoid traffic congestion during the convoy's movement, the passage of heavy vehicles was temporarily restricted on some sections of the highways.
Under the supply plan of Russia's state-owned nuclear energy corporation Rosatom, a total of 163 uranium fuel assemblies are scheduled to be delivered in seven cargo flights for the plant's second unit.
In addition, another 48 assemblies for refuelling the first unit are planned to be supplied in two consignments. This brings the total number of planned shipments to nine. Rosatom aims to complete the remaining fuel deliveries in November and December.
The additional fuel imports for the first unit are primarily intended to support routine maintenance and preparations for fuel replacement. According to project-related information, part of the fuel used in the unit will need to be replaced after approximately one and a half years of operation.
Under the agreement, Russia will supply nuclear fuel to the plant for the first three years. Bangladesh will subsequently have to import fuel at scheduled intervals for replacement.
Built with Russian technology and assistance, the Rooppur Nuclear Power Plant has two reactors using VVER-1200 technology. Each unit has a generation capacity of 1,200 megawatts. Once both units become fully operational, the plant is expected to supply a combined 2,400 megawatts of electricity to the national grid.
Meanwhile, the plant's first unit has begun supplying electricity to the national grid on a trial basis. It was connected to the grid for the first time at 3:16pm on November 17, initially supplying around 350 megawatts. During testing, generation reached a maximum of 375 megawatts. After supplying electricity for approximately eight and a half hours in the first phase, the unit was disconnected from the grid to allow further technical tests.
According to sources concerned with the project, it may take several more months to complete the various stages of trial operations. Each stage will involve testing the reactor, turbine, generator, safety systems and the compatibility of electricity supply with the national grid. Once these tests are completed satisfactorily, the plant will require the necessary approval from the Bangladesh Atomic Energy Regulatory Authority. Generation capacity will then be increased gradually.
The government's target is to begin commercial electricity supply from the first unit at full capacity by February 2027, following the completion of all required tests and regulatory approvals. However, achieving this timeline will depend on meeting all technical and regulatory requirements within the stipulated period.